Hi to everibody

Do you know some RPN under which i stop making corrective actions?, i suposse at some level can i stop making recommendations and corrective actions, and if is there any regulation about it.

Thank you so much

You may be mixing some terms.

RPN is for risk assessment. You define (per your Risk Management SOP) the point at which the risk is acceptable. If the RPN for a particular risk is above the threshold, you would be expected to implement controls to bring it below the threshold. If it is not possible to do so, you have to justify why the benefits outweigh the risk.

Corrective Actions are for non-conformances. For CAs, you have to identify the root cause, fix the problem, fix whatever is causing the problem, and implement fixes to ensure the problem doesn’t occur again. You then have to confirm that the fixes were effective.