I have to do requalification of BMS system. Our BMS system including SCADA for HVAC system.

Which tests I have to performe during requalification?

Thank you very much,

Slavica

What was done for initial qualification? Look at that and do a risk-based assessment to help guide what is to be tested. Be sure to document it with rationale for why any tests were excluded.

What is driving the re-qualification? Changes? If so, you may want to also add some new tests on top of the existing ones.